Καθυστερήσεις Σύνδεσης ΑΗΚ: Η Κρυφή Πρόκληση που Αντιμετωπίζουν οι Νέοι Ιδιοκτήτες Σπιτιών στην Κύπρο
In Cyprus, many newly constructed homes stand ready for their owners yet remain unoccupied — not due to any fault of the buyers or builders, but because the essential utility of electricity is missing. The Electricity Authority of Cyprus (EAC) has been facing significant delays in connecting power to new properties, in some cases leaving homeowners waiting for months and even up to two years.
Delays: Impacts Beyond the Property
AKEL MP Valentinos Fakontis has spotlighted these delays in Parliament, highlighting the growing frustrations of families, businesses, and developers. Finished homes have reportedly stayed without power for half a year or longer, especially when a new electricity network needs building from scratch. This issue doesn’t only affect homeowners but also stalls construction progress and halts development on newly subdivided plots due to incomplete electrical infrastructure.
Lengthy and Complex Approval Processes
The process to connect electricity involves multiple steps — applications, technical studies, consent approvals, adherence to technical terms, infrastructure works, and final inspections. According to Mr. Fakontis, the entire sequence can sometimes extend beyond two years, creating uncertainty and limiting property usability.
Financial and Emotional Toll on Families and Builders
Buyers who have secured mortgages may be forced to pay both mortgage installments and rental fees simultaneously because they cannot move into their new homes. Builders face delayed handovers, increased financial pressure from extended loans, potential penalties, and disrupted cash flows.
This bottleneck impacts Cyprus’ construction sector and investment climate adversely, with delays casting a shadow over the country’s reputation among investors and potential homeowners alike.
Calls for Improved Staffing, Planning & Procedures
Despite acknowledging the hard work and overtime efforts of EAC staff, Mr. Fakontis stresses that proper staffing levels, strategic planning, and modernized procedures are crucial. He advocates integrating electricity network planning early in the construction cycle to ensure infrastructure is ready when homes reach completion.
Specifically, clearer deadlines, streamlined application processes, and better resource allocation could significantly alleviate the waiting times.
Parliamentary Action Underway
The Parliamentary Committee on Energy, Commerce, Industry and Tourism is set to investigate the causes of these delays and explore viable solutions to prevent future holdups.
For those looking at alternative options, exploring Φτηνές κατοικίες και βίλες προς πώληση Κύπρος might present opportunities in areas with less connection congestion, while investors interested in land may find Οικόπεδα προς πώληση with established utilities ready for development.
It remains unacceptable for fully built homes to remain uninhabitable due to ongoing power connection delays. Urgent reforms are needed to protect homeowners, support builders, and secure Cyprus’ position as a reliable real estate destination.
Stay updated with INDEX.cy for the latest real estate news and in-depth market analysis in Cyprus.
Συνέχισε να διαβάζεις
33 αγγελίες στην Ορμήδεια, Λάρνακα, αναλύθηκαν. Οι κατοικίες κοστίζουν 350,000 ευρώ με μέση τιμή, τα οικόπεδα από 48,750 ευρώ. Δείτε τις ζώνες προϋπολογισμού, τους ελέγχους γης και τα βασικά...
Η Κύπρος Προωθεί την Εγγραφή Αγροτικών Οδών για την Απελευθέρωση Αναπτυξιακού Δυναμικού Από τις αρχές του 2024, η Κύπρος έχει λάβει σημαντικά μέτρα για τη βελτίωση της πρόσβασης...
Η Κύπρος Προχωρά σε Υποχρεωτικές Επιθεωρήσεις Ασφάλειας Κτιρίων Εν μέσω Διαφωνίας για τη Χρηματοδότηση Σε απάντηση στις αυξανόμενες ανησυχίες σχετικά με την ασφάλεια των κατασκευών, η Κύπρος διερευνά το…